Slope Indicator
12123 Harbour Reach Dr Mukilteo, WA, USA 98275
Tel 425-493-6200 Fax 425-493-6250
|
Countering Casing Buoyancy
Why Casing Floats in Grout
Grout backfill has a higher density
than water-filled casing. During installation, when the grout is still a fluid,
it exerts an uplift force on the bottom cap of the casing. This uplift force is
greater than the down force exerted by water-filled casing. The net uplift can
be calculated as the density of grout minus the density of water filled casing
x depth of casing x area of bottom cap. Lateral forces do not contribute to uplift.
The density of water-filled casing is about 62.4 pounds per cubic foot or
1000 kg per cubic meter. The density of ABS casing and the density of water
are nearly the same. The density of bentonite-cement grout is about 80 pounds
per cubic foot or 1280 kg per cubic meter. The area of the bottom cap of 2.75"
(70mm) inclinometer casing is 0.0412 square feet or 3.8485E-3 square meters.
Thus if the bottom cap is 100 feet deep, the uplift pressure on the 2.75 inch
bottom cap will be about 72.5 pounds or 32.3 kg.
The Worst Way to Counter Buoyancy
Unfortunately, the easiest way
to keep the casing in place - holding the casing down from the top - is also the
worst way. The uplift force acts on the bottom of the casing, so if the casing
is held in place from the top, the casing goes into compression. When the casing
goes into compression, it tends to snake from side to side in the borehole. This
problem is particularly severe in large diameter boreholes and in deep installations,
where the uplift force is largest and where portions of the borehole may be enlarged.
Snaked casing increases the potential for:
- Kinked or Separated Casing: The combination of compressive
force and eccentric loading (due to snaking in enlarged diameter boreholes)
can produce strong bending moments in the casing. In some severe cases, this
bending moment has caused snap-together joints to fail where the glue-and-rivet
joints do not.
- Depth Errors: In snaked casing, slight changes or errors in the
positioning of the probe will produce reading errors. The larger the curvature,
the larger the error. For example, if the change of inclination between
adjacent
reading increments is two degrees, and the probe is positioned 25 mm from
the correct depth, the resulting error in displacement would be 1 mm.
Better Ways to Counter Buoyancy
- Suspend a steel pipe or drill rods inside the casing. For
the best results, suspend the pipe just an inch or so off the bottom cap of the
casing.This ensures that the steel pipe remains straight and avoids resting the
full weight of the pipe on the bottom cap. As the casing rises to meet the pipe,
the down force of the pipe is activated to keep the casing in place. The main
drawback to this method is that you must use the drill rig to suspend the pipe
or you must return with the drill rig to retrieve the pipe. A variation is to
rest the pipe on the bottom cap, which you must reinforce.
Pre-install an anchor at the bottom of the casing. Simple prong
anchors or packer types have been used. Slope Indicator has produced several prototypes
of such anchors. Different soils may require different types of anchor.
- Pre-attach a weight to the bottom of the casing. This method
requires a weight, a safety line to prevent casing from sinking, a borehole
drilled deeper to accommodate the weight, and calculation of the uplift
force.
It is best used in shallow boreholes.
- Grout the borehole in stages. The uplift force of grout
varies with the height of the grout column. If the column is short, the
uplift force
is low and the casing can be held in place by its own weight or with
very little down-force applied from the top. When the grout sets, the
bottom cap
is isolated from the column of grout and there is no surface for the
uplift force to act on. No more than two or three meters to 3 m need
to be grouted
in the first stage. If the normal bentonite/cement grout is used it
needs to set for at least 12 hours before second-stage grouting. Avoid
use of a
quick-set grout, since the heat of hydration could melt and deform the
plastic. The two stages can be placed via an outside tremie pipe. Alternatively
the
first stage can be placed before lowering the casing, provided that
all is done efficiently so that there is no chance of the grout setting
prematurely.
If grout valve method is used, first stage grouting can be done through
the valve, and then the valve is abandoned. An outside tremie pipe for
the second
stage is lowered with the casing, with its bottom at the level planned
for the top of the first stage. After first stage grouting, the excess
is flushed
out via the tremie pipe, and then this is raised until the first stage
has set.
- Fill the casing with drilling fluid that is heavier than the grout. This
is a sure and easy method, but requires disposal of the drilling fluid.
|