Application Stories
Sydney,
Australia
Highly-stressed rock and six brick-lined rail tunnels complicated a deep excavation
in Sydney's central business core.
The project involved the removal of 100,000 cubic meters of sandstone for the
basement of Genting Centre. Previous excavations in the area produced deformations
of up to 1 mm per meter of excavation and caused damage to buildings and rail
tunnels. The damage was believed to have been due to the relief of relatively
high horizontal stresses in the rock.
The
average depth of the Genting Centre excavation would be 30 meters, extending to
36 meters at one location, so there was great potential for damaging deformations.
In addition, the George Street face of the excavation would approach within three
meters of the nearest rail tunnel.
Authorities placed strict controls on deep excavations in the area. In particular,
the Rail Service Authority stipulated that their tunnels must be monitored during
excavation and that displacements between the tunnel walls must be limited to
10 mm. The RSA also required the developer to post a substantial bond to cover
the cost of repairs should the tunnels be damaged.
Recognizing the need for a geotechnical and civil engineering consultant, the
developers retained Golder Associates, who had already conducted geological investigations
and stress analyses at the site for a previous proposal. Golder Associates developed
a geotechnical model to predict the field performance of the rock and the retention
systems, advised on excavation and underpinning methods, evaluated design parameters,
and implemented a monitoring program. The aim of the analyses was to provide guidance
to allow efficient and safe excavation of the basement.
Excavation and Support
The excavation took place over a 12 month period. The George Street face (adjacent
to the rail tunnels) was retained by an anchored contiguous bored pile wall to
about 8 meters depth. Permanent support in this zone will be provided by floor
slabs. Below that depth, a system of ground anchors and rockbolts was used. Elsewhere,
the building is to be constructed independently from the excavation. Temporary
support was provided by an anchored soldier pile and timber lagging system. Below
this, support was provided by a combination of rockbolts and 75mm-thick, mesh-reinforced
shotcrete. A total of 1,000 fully encapsulated rockbolts were used to provide
long-term support.
Instrumentation
Instrumentation,
which was installed before construction began, included:
Surface survey points were set up around the perimeter of the excavation
and on adjacent buildings. At the completion of the excavation, the maximum displacement
recorded was 15 mm on the southern side of the excavation. The critical George
Street survey points showed up to 4 mm of displacement. The drawing at right shows
maximum displacements. Inclinometers
, shown in the drawing, were installed along the George Street face to monitor
movements adjacent to the tunnels and measure shear movements along major bedding
horizons. The maximum displacement recorded by the inclinometers was 6 mm toward
the excavation at a level corresponding with a bedding parting. Contrary to expectations,
displacement plots often showed movement away from the excavation in the upper
half of the wall. However, this was generally consistent with survey data and
was attributed to a combination of stressing of anchors and stress-relief effects
due to the construction techniques used when the tunnels were constructed. Incremental
displacements between readings were small, consistent, and assessed to be accurate.
Load cells
were installed on the collar of selected ground anchors along George Street. Problems
had been reported by others in achieving adequate anchor loads during construction
of the Coopers & Lybrand Tower, on the other side of George Street. Initial
loads showed a decrease but then stabilized.
Tunnel survey points were installed in the lining of the railway tunnels.
Monitoring stations were set up at three locations along both the upper and lower
tunnels next to the excavation. The maximum lateral displacement of the walls
was 8 mm, and the maximum downward displacements of the roof were 3 mm.
A tape extensometer
to was used to monitor tunnel convergence. Maximum displacements at three locations
were between 1 mm and 4 mm divergence (dilation).
Vibration monitors were installed to ensure that maximum velocity did
not exceed 20 mm/s during construction of the pile wall, installation of ground
anchors, and the excavation process.
Summary
The Genting Centre excavation was successful. Some minor cracking was observed
in adjacent buildings, but once filled, no further opening was observed. The finite
element modelling adequately represented the overall deformation pattern and provided
guidance for safe and efficient excavation and construction. Actual movements
recorded by the instrumentation were smaller than predicted, and all displacements
were within acceptable limits. Instrumentation proved to be a cost-effective investment.
The structural engineers on the project were Taylor, Thompson, and Whitting.
The excavation contractor was Ward Civil Engineering. The owner of the site is
Genting Australia Investment Holding Pty Ltd.
Thanks to Golder Associates, Australia for this story. It is excerpted from
a technical paper entitled, "Genting Centre, Sydney - Deep Excavation Adjacent
to Railway Tunnels" which was presented at the 8th ANZ Conference on Geomechanics
in 1999.
Golder Associates can be contacted at 88 Chandos Street, St Leonards, NSW
2065,
Australia. Tel +612-9439-3611, Fax +612- 9436-0693, www.golder.com
.
|